description: "**Audience:** bookkeeper, admin · **Last updated:** 2026-06-07 · [Edit on GitHub](https://github.com/phreesoft/bizuno/edit/main/docs/04-modules-in-depth/03-inventory/04-work-orders-production.md) # Work Orders / Production A **work order** (WO) is the shop-floor side of building an [assembly](/docs/assemblies/): it tracks the production steps, who did and checked each one, and…"
url: "https://www.bizuno.com/docs/work-orders-production/"
updated: "2026-06-18"
category: Inventory
---

# Work Orders / Production

**Audience:** bookkeeper, admin · **Last updated:** 2026-06-07 · [Edit on GitHub](https://github.com/phreesoft/bizuno/edit/main/docs/04-modules-in-depth/03-inventory/04-work-orders-production.md)

# Work Orders / Production

A **work order** (WO) is the shop-floor side of building an
 [assembly](/docs/assemblies/): it tracks the production steps, who did and checked
 each one, and any data captured along the way — and when the build is done, it
 posts the accounting automatically. This is where Bizuno crosses from "accounting
 app" into **light MRP**.

> **Light** is the operative word. Work orders give you a stepped, signed-off
>  build process with stock allocation — not work centers, routings, or capacity
>  planning. (Labor *cost* you can capture, via labor items on the
>  [bill of materials](/docs/assemblies/#costing-labor-and-overhead).) Read
>  [Honest scope](#honest-scope) before you commit a real manufacturing operation
>  to it.

---

## Two records, two jobs

| Record | Journal | Role |
| --- | --- | --- |
| **Work Order** | jID 32 | The workflow tracker — steps, signoffs, allocation |
| **Assembly** | jID 14 | The GL posting of the actual build |

The work order is **planning and execution**; the assembly is the **accounting**.
 When a work-order step that's flagged to post completes, Bizuno creates and posts a
 jID 14 [assembly](/docs/assemblies/#building-what-posts) for you — consuming
 components and producing the finished item. The two are linked by reference number.

---

## The Production Manager

Work orders live under the Production Manager (`inventory/build`), with child
 screens for the step **Designer** and the **Tasks** list. The controller methods
 map to the lifecycle:

| Action | What it does |
| --- | --- |
| `add` | Start a WO by choosing the assembly SKU to build |
| `edit` / `save` | Set/adjust quantity and due date; re-allocates components if qty changes |
| `details` | Show the production-steps table with the current step highlighted |
| `saveStep` | Advance a step — record manufacturing & QA signoffs, capture any required data, and (if the step is flagged) auto-post the jID 14 build |
| `delete` | Remove the WO — un-posts the jID 14 if it was already assembled |
| `allocateAdj` | Reserve component stock against open WOs (`qty_alloc`) |

### Lifecycle and status

A work order's headline state is the `closed` flag (0 = open, 1 = closed), with
 `post_date` as the create date, `terminal_date` as the due date, and `closed_date`
 stamped when the final step completes.

Within a WO, the **production steps** are stored as metadata. Each step carries:

- a **complete** flag,
- **manufacturing** and **QA** signoffs (`mfg_id` / `qa_id`) with their dates,
- an optional **captured value** (`data_value`) when the step requires a reading
   or measurement.

So a build progresses step → step, each one signed off (and optionally
 QA-checked and data-stamped), until the posting step fires the assembly and the
 order closes.

### Component allocation

If a WO is set to allocate, opening it **reserves** its components by raising
 `qty_alloc` on those items — so the stock shows as spoken-for and won't be
 double-committed. Changing the WO quantity re-allocates; deleting or completing it
 releases the reservation. This is how build-to-order coexists with normal sales
 demand on the same stock.

---

## Security: the parent-menu access bridge

Work-order access is governed by the `woProd` security key. There's a wrinkle
 worth knowing if you administer roles:

The role editor only exposes checkboxes for the **leaf** screens (the Designer and
 Tasks children), not for the Production Manager parent. To keep the parent
 reachable, Bizuno (since **7.3.9**, via `removeOrphanMenus()`) gives a routable
 parent menu the **maximum access level of its children** — so granting a user the
 child screens automatically grants the parent it lives under.

Practical upshot: **grant the child permissions and the Production Manager opens**;
 you won't find (or need) a separate checkbox for the parent.

---

## Honest scope

What work orders **do**:

- Stepped builds with manufacturing + QA signoff per step
- Optional data capture per step
- Component allocation / reservation (`qty_alloc`)
- Automatic GL posting of the build (jID 14) on completion
- Tie a build to the assembly definition for repeatability

What they **don't** do — by design, so you can plan around it:

- **No work centers, routings, or capacity/scheduling.** Steps are a checklist,
   not a routed operation through resources.
- **Labor cost, but not labor *time*.** You can fold labor and overhead **cost**
   into the build by putting labor items on the
   [bill of materials](/docs/assemblies/#costing-labor-and-overhead); what steps
   don't do is capture actual hours worked or feed a time clock.

For batch builds, kit assembly, itemized labor cost, and a documented sign-off
 trail, this is a genuine asset. For full discrete or process manufacturing with
 routed work centers, treat it as a stepping stone, not a destination.

---

## Quality stop-work and the dashboard

A work order can be halted for a quality problem, and the place that surfaces is
 the **Quality module's stop-work tickets** ([CA/PA tickets](/docs/ca-pa-tickets/)).
 There is **no automated data link** between a quality ticket and a specific work
 order — holding a build for a quality issue is a human-coordinated process, not a
 system gate. What gives management *visibility* into it is the **Stop-Work
 dashboard** (`qa_stop_work`), which lists open stop-work tickets at a glance, each
 linking through to the corrective-action record.

> **About dashboards.** A Bizuno dashboard is a summary widget that gives you
>  at-a-glance data on the page where it's relevant. Each dashboard declares a
>  **category** matching a major menu heading (Customers, Vendors, Inventory,
>  Banking, General Ledger, Quality, …), and Bizuno shows it on that heading's
>  landing page; dashboards can also be placed on the **home page** so management
>  sees the most important numbers the moment they log in. A user adds the
>  dashboards they want from the available set for that page.
>
>
>
> The Stop-Work dashboard ships under the **Quality** category. To put critical
>  safety/quality status in front of management immediately, add it to the **home
>  page** dashboards — that's exactly the kind of summary the home dashboard is for.

---

## Related

- [Assemblies](/docs/assemblies/) — the bill of materials and build costing
- [History and costing](/docs/history-and-costing/) — how component cost is drawn
- [CA/PA tickets](/docs/ca-pa-tickets/) — the (separate) Quality module
- [Roles and security](/docs/roles-and-security/) — the access model behind `woProd`